Concrete is poured into the stem wall forms.
Report and photo by Dennis Casebier
Craig Merriam and his three-person concrete crew rolled onto the property at 6:45 AM this morning. Within fifteen minutes the first of three concrete trucks from Mohave Valley arrived. The other two trucks of "mud" showed up at 45 minute intervals.
Pretty soon Gus and Stella and I were out there, joined later by Jo Ann and John Harrington. So there were plenty of supervisors! These three loads were for the footings and it turned out three full loads was not quite enough. The shortage will be made up when the slab is poured.
Craig had hoped to pour the slab tomorrow (Friday) but the forecast is for 14 MPH winds early in the morning, building up to something closer to 20 MPH by the afternoon. Craig says that's too much so the slab will not be poured tomorrow. The next window of opportunity will be Monday.
It was cold this morning - right at 30 degrees. We had ice on the bird water for the first time this season. But there was very little breeze so it was not uncomfortable.
By 9:00 AM, the last of the three concrete trucks were cleaning out.
Around 1:00 PM, I noticed an extra white pickup at the work site. I found general contractor Dan Cordova there. He was pouring over the plans and had detailed questions about measurements and a few other items. I got John Harrington so we could all go over the details together. We had about an hour-long meeting over the details.
General contractor Dan Cordova is a carpenter by trade. His crew will be doing the framing. He had hoped to begin framing on Monday, but now that will have to be delayed. Dan says they'll start framing Tuesday and have the first story done by the end of the week. He said the lumber will arrive Monday and he showed me where he wants it placed.
Craig Merriam's crew is still out there working with the forms and concrete poured this morning.
I went to the pantry and fetched the notebook with all the photos we have of the Depot for show and tell. Everyone was very interested.