Report by Dennis Casebier
It was a busy day at Goffs today.
Brandon the painter had stayed overnight in the Dutchmen Trailer. Phil Motz provided him dinner last night and they sat out under the Green Tree working on the world's problems until a late hour. Indications are they made a lot of progress. Brandon finished up his painting and was gone by about noon today. I believe that's the last we'll see of the painter.
General Contractor Dan Cordova was here this morning. He got the plywood backboard mounted on the north wall of the north Freight House room and Brandon painted it. This backboard will be used for centralizing the phone, data, Internet, and CATV wiring.
Donnie Millard of "Desert Air" showed up during the morning and was here until 4:00 PM. He activated the heating, air conditioning, and humidity control systems. Just before he left, Jo Ann, Phil and I assembled over there. The whole building was chilled. On a day with the humidity standing at 35% and the temperature at 104 degrees -- it was wonderful.
Tuesday, July 15, 2008
Thursday, July 10, 2008
Inspection and phones
Report by Dennis Casebier
Inspector Steve Given was on site today with general contractor Dan Cordova developing a list of final items needing to be done before finalization.
The phone rang just now in the Casebier house. It was Phil Motz calling from the Library Depot! Then he called back on our second (fax) line! So the Library/Depot is in communications with the rest of the planet! All thanks to very hard and hot work by Mr. Motz with a little help at times.
Inspector Steve Given was on site today with general contractor Dan Cordova developing a list of final items needing to be done before finalization.
The phone rang just now in the Casebier house. It was Phil Motz calling from the Library Depot! Then he called back on our second (fax) line! So the Library/Depot is in communications with the rest of the planet! All thanks to very hard and hot work by Mr. Motz with a little help at times.
Labels:
Phil Motz
Tuesday, July 8, 2008
Odds and ends
Report by Dennis Casebier
General Contractor Dan Cordova and two of his crew arrived at about 7:00 AM this morning. They are working on Library/Depot odds and ends. Finishing up!
Here are some upcoming activities;
General Contractor Dan Cordova and two of his crew arrived at about 7:00 AM this morning. They are working on Library/Depot odds and ends. Finishing up!
Here are some upcoming activities;
- Tomorrow 9 July the safety glass will be put into three upstairs windows as required.
- Thursday we are scheduled to have the final inspection on the building (we have a bottle of champagne chilling in the frige.
- Next Tuesday the HVAC guys will be out and fire up the air conditioning systems.
- That leaves the one door that needs to get painted green. Dan said Brandon & Co will be out to do that.
Labels:
Phil Motz
Sunday, July 6, 2008
Ditch dug for the phone lines
Much hard work has been accomplished over the past few days in getting the phone lines to the new building. It wasn't until mid-week that we were able to settle with Dan Cordova on a point to bring the phone lines into the building.
In order to accomplish it we had to dig a ditch a little over 200 feet long to carry the line from the Power House to the northwest side of the building where the line will enter. But the job is done and Phil will now be able to get the phones through into the building before he leaves on the 17th.
I say the job is done but it isn't exactly. We still have to string the line from the Power House to the power pole near Lanfair Road. Phil and I can do that.This important and difficult work has been accomplished over a holiday weekend in intense heat - by Phil Motz, Hugh Brown, and myself. It was very hot working out there on that ditch!
Labels:
Dennis Casebier,
Hugh Brown,
Phil Motz
Wednesday, July 2, 2008
Baseboards and clean-up
Report by Dennis Casebier
Dan Cordova and two of his guys showed up at about 8:00 AM. They will be putting in the baseboards and cleaning in and around the building. He figures they likely won't get done today and will be back tomorrow.
One of the on-demand water heaters in the Lounge/restroom isn't working. The plumber will be coming out next week to replace it.
Phil has procured all the materials he needs to complete the phoneline to the Library/Depot.
Dan Cordova and two of his guys showed up at about 8:00 AM. They will be putting in the baseboards and cleaning in and around the building. He figures they likely won't get done today and will be back tomorrow.
One of the on-demand water heaters in the Lounge/restroom isn't working. The plumber will be coming out next week to replace it.
Phil has procured all the materials he needs to complete the phoneline to the Library/Depot.
Labels:
Phil Motz
Tuesday, July 1, 2008
Finishing touches on the water system
Report by Dennis Casebier
There have been no workers here yet this week. Dan Cordova and crew are expected to be here as early as tomorrow to put in door closers, base boards, and maybe an illuminated address sign.
Phil Motz has been busy working with the water system. Both the north and south systems are on line and we are using water out of both. Also he obtained materials in town yesterday to put in lights in the Power House and the new north Pump House. Lights are designed to come on when Deep Well #2 pump is on and when the booster pumps in the north Pump House are on.
Phil has also picked up ceiling fans which he will install in the new building.
It's very hot in Goffs today and along the Colorado River Valley.
There have been no workers here yet this week. Dan Cordova and crew are expected to be here as early as tomorrow to put in door closers, base boards, and maybe an illuminated address sign.
Phil Motz has been busy working with the water system. Both the north and south systems are on line and we are using water out of both. Also he obtained materials in town yesterday to put in lights in the Power House and the new north Pump House. Lights are designed to come on when Deep Well #2 pump is on and when the booster pumps in the north Pump House are on.
Phil has also picked up ceiling fans which he will install in the new building.
It's very hot in Goffs today and along the Colorado River Valley.
Labels:
Phil Motz
Thursday, June 26, 2008
Flooring finished on the second floor...
Report and photos by Dennis CasebierThe flooring for the second floor of the Depot, the Lounge, and the restroom were finished at about 3:00 PM today.
...the Lounge...
...and the restroom.
Wednesday, June 25, 2008
Depot flooring begins
The flooring crew, consisting of Kelly Binns, Ed Hardesty, and Donna May, arrived mid-morning. They started on the first floor of the Depot.
First they cleaned the floor, then put down some kind of foam sheeting, and now they are laying maple tongue and groove pattern, perco-type flooring on top of that. At 2:00 PM they were about two-thirds of the way done with that room.
Here at the end of the day, the flooring is complete on the first floor of the Depot. Also they've cleaned the floor in the lounge and bathroom and are putting glue down. We are asked not to go in there this evening or we might have to stay forever!
A window guy is here working on loose molding. There'll be some other glass guy later to replace some of the glass upstairs.
Very warm and windy today but it isn't impacting their work day since the workers are inside.
Monday, June 23, 2008
Air conditioning units rewired
Report and photo by Dennis CasebierThe electrician arrived mid-morning and did some rewiring of control boxes by the air conditioning units on the west side of the Library/Depot.
Saturday, June 21, 2008
Flooring delivery and plumbing leak
Report by Dennis Casebier
The flooring guys, led by Jim O'Connor, were here before noon. They dropped off a bunch of flooring (apparently not all of it) and then departed for Laughlin. They said they'd be back Wednesday morning with the rest of the flooring to do the job.
The plumber came in some time this morning. He found a leak. It was in a pipe that got punched with a nail during some of the finish work around the toilet. It's now been fixed. The plumber adjusted the pressure in the pump house to 56 pounds.
Very hot in Goffs today. 110 degrees at 3:30 PM on the west porch.
The flooring guys, led by Jim O'Connor, were here before noon. They dropped off a bunch of flooring (apparently not all of it) and then departed for Laughlin. They said they'd be back Wednesday morning with the rest of the flooring to do the job.
The plumber came in some time this morning. He found a leak. It was in a pipe that got punched with a nail during some of the finish work around the toilet. It's now been fixed. The plumber adjusted the pressure in the pump house to 56 pounds.
Very hot in Goffs today. 110 degrees at 3:30 PM on the west porch.
Thursday, June 19, 2008
Rain gutters and bollards
Report and photos by Dennis CasebierThe rain gutter guys (three of them) showed up this morning. Jo Ann and I were just
leaving for a quick business trip into town. I figured they would still be here when we got back at about 2:00 PM, but they were gone already. Hugh reports the job took about four hours. So the gutters are all in place.
Also, Dan Cordova and a helper were here this morning finishing up the bollards they started yesterday. These are metal posts designed to prevent people from driving their vehicles into the new building.
The plumber is expected to be back on Saturday of this week to fix a leak that has developed in one of the walls.Dan is picking off the few remaining tasks. The last big one will be to put the flooring down and I understand that is to be done next week.
We are nearing completion.
Wednesday, June 18, 2008
Painting the handicapped parking
Dan Cordova and crew are here preparing to paint the the handicapped parking area with the appropriate blue and white emblems. They will also install curb stops and yellow-painted bollards to protect the building.
The flooring contractor, Jim with Hardesty Custom Floors, will be stopping by on Saturday to drop off some of the flooring to be installed next week, starting Wednesday. After that, Dan will be back to install the baseboard and the painter will be back to touch-up everything.
Saturday, June 14, 2008
Friday, June 13, 2008
Loading dock poured and stamped
Today was the fullest day around the construction site we've had in quite awhile.
The concrete man Craig Merriam, his deputy Jody, and his wife Terry, spent the night at Goffs in anticipation of arrival of a concrete truck by 5:00 AM.
The concrete truck arrived on time. Craig & Co. soon had it lined up with the loading dock forms alongside the Freight House and began dumping from the nine yard load. Even prepared as we were for this special load, it it was surprising to see brown-colored concrete coming down the chute!Meanwhile, the electrician arrived mid-morning and did some rewiring of control boxes by the air conditioning units on the west side of the building.
Thursday, June 12, 2008
Parking slab poured
The concrete truck came in a little before 5 AM and we didn't catch it. The truck poured the handicapped parking slab and also the small slabs "stoops" outside each door.
There will be just one more truck tomorrow. It will be carrying the colored concrete for the loading dock. Today's concrete crew are Craig and Jody. They'll be staying overnight in our trailers to deal with the concrete truck tomorrow morning.
Also Dan Cordova is here. He's installing grab rails in the restroom. He says the electrician will be here tomorrow to hook up the air conditioning units.
Sunday, June 8, 2008
Plumbing wrap up
Plumber Tim Henry arrived this morning at about 10:30 AM. He plans to be here only about an hour and a half after which he'll have the plumbing all done. I believe he has a toilet with him, so maybe we'll be able to perform a test flush in our new building!
Fierce wind in Goffs today.
Saturday, June 7, 2008
Intrusion alert system installed
Report by Dennis Casebier
Dave Mongrain of security firm, Alarm Team, has been here working on the security system. He'll be leaving here shortly. He has the intrusion alert system all hooked up. We did a dynamic test of the big alarm that goes off if someone intrudes.
Dave Mongrain of security firm, Alarm Team, has been here working on the security system. He'll be leaving here shortly. He has the intrusion alert system all hooked up. We did a dynamic test of the big alarm that goes off if someone intrudes.
Thursday, June 5, 2008
Concrete plans
I met this morning with building inspector Steve Given and concrete subcontractor Craig Merriam. Mr. Given went over the loading dock plans with Craig and they have reached agreement -- so Craig can proceed.
Craig said he was originally figuring to have concrete up here Monday but he's looked ahead with the weather and says the wind is supposed to be blowing so he likely won't figure on meeting that schedule. He plans to pour Tuesday or Wednesday of next week, depending upon the weather
Craig says he'll be back tomorrow to finish up his preparations.
Wednesday, June 4, 2008
Loading dock forms constructed
General Contractor Dan Cordova and a couple of guys were here all day working on odds and ends.
Cement sub-contractor Craig Merriam was here with crew working on forms and putting in rebar for "flat work," which are the handicapped parking area, sidewalks and the forms for the loading dock.
It was on the cool side today and very windy out of the west.
Tuesday, June 3, 2008
Flatwork begins
Cordova and crew are here this morning. His crew is busy finishing installation of cabinets in the Lounge.
The concrete man, Craig Merriam, has come in with his crew to get started on the final "flat work" such as the parking pads, sidewalks, stoops, and loading dock.
I reviewed progress with Dan Cordova. The bottom line is that he'll be nearly done by the end of next week. Yet to do;
The air conditioning guy will be in with his equipment that goes outside on the slab later this week. The electrician will come in after him to hook up the A/C equipment up. Preparations for the final concrete work is in progress.
The building inspector is scheduled to be here Thursday to approve plans for the loading dock.
It is going to be another warm day in Goffs. It was well over 90 degrees yesterday and today looks like a repeat.
Monday, June 2, 2008
Lounge cabinets arrive
Dan Cordova arrived this morning at about 8:00 AM with two of his sons as crew. They have brought the cabinets for the Lounge. They plan to unpack and install them today.
Day says the concrete man will be here tomorrow to begin on the flat work for the parking area, sidewalk, and stoops.
Dan is closing in on the job. There will be some waiting for the arrival of the special order flooring material.
Thursday, May 29, 2008
Let there be light!
Yesterday evening after dark, we looked over towards the Library/Depot and beheld a wonderful thing - it was lighted up!The electrician had gone home and turned the outside lights on - there's a lamp by each door.
Jo Ann and I went over to turn the lights out. Of course we walked all around the building turning other lights on. They all work! And what wonderfu light it is. We're going to have really good light to work by.
This morning I had the pleasure of showing a reporter from the Needles Desert Star through the building. It "shows" very well.
Then at about noon today, Hugh and Carol Brown showed up so we got to go play with the lights again. It appears the building is fully electrified. All the electrician will have to come back for is to hook up the outdoor A/C units when they get installed.
Next is making arrangements to get the security system completed, install the cabinets in the lounge, install the flooring, and lay the concrete flat work around the building.
There is light in the end of the tunnel!
Tuesday, May 27, 2008
Flourescent light fixtures are up
Report by Dennis Casebier
Two electricians were here much of today. Jo Ann and I inspected progress later in the day. The flourescent light fixtures are up in most places. The "on/off" wall switches seemed to be mostly in place. At least one wall plug was "hot" as there was a glow light illuminated at the end of an extension cord. The building is coming to life and is expected to be pretty much electrified by the day-after-tomorrow.
Two electricians were here much of today. Jo Ann and I inspected progress later in the day. The flourescent light fixtures are up in most places. The "on/off" wall switches seemed to be mostly in place. At least one wall plug was "hot" as there was a glow light illuminated at the end of an extension cord. The building is coming to life and is expected to be pretty much electrified by the day-after-tomorrow.
Monday, May 26, 2008
Electrical fixture installation begins
Report by Dennis Casebier
Fred Compton the electrician arrived this morning at about 9:00 AM. He says he plans to be here through Thursday and sometime during that period he'll "power up" the new building. The electrical will be mostly done then except for a quick trip out after the lounge cabinets and the air conditioning are installed.
Fred Compton the electrician arrived this morning at about 9:00 AM. He says he plans to be here through Thursday and sometime during that period he'll "power up" the new building. The electrical will be mostly done then except for a quick trip out after the lounge cabinets and the air conditioning are installed.
Friday, May 23, 2008
Quiet week and rain
Report by Dennis Casebier
No work on the Library/Depot the last couple of days. Next week should be exciting. I'm understanding the electrician will be back to install the fixtures, and then we'll be able to power up! Things are moving along.
We did have a special blessing today in the form of RAIN! It has been cloudy for a couple of days and the air got especially cool last night. It looked like rain all day and then we had thunder and lightning beginning at about 3:15 PM.
We closed the breakers on the deep well pumps to lessen the chance of damage to them. Then here came the rain. It was a nice little rain; I would guess at least a quarter and maybe a half inch. It was over in about half an hour. First rain we've had since January, I think.
No work on the Library/Depot the last couple of days. Next week should be exciting. I'm understanding the electrician will be back to install the fixtures, and then we'll be able to power up! Things are moving along.
We did have a special blessing today in the form of RAIN! It has been cloudy for a couple of days and the air got especially cool last night. It looked like rain all day and then we had thunder and lightning beginning at about 3:15 PM.
We closed the breakers on the deep well pumps to lessen the chance of damage to them. Then here came the rain. It was a nice little rain; I would guess at least a quarter and maybe a half inch. It was over in about half an hour. First rain we've had since January, I think.
Subscribe to:
Posts (Atom)
