Report by Dennis Casebier
Actual construction work commenced when Sam and Mike Lehman of "Lehman Excavators" out of Joshua Tree started work forming the pad of dirt that the Library/Depot will be built upon. The pad is designed to raise the floor of the Library one foot above "grade" to avoid the potential of water intrusion during a flash flood.
Later in this week the concrete subcontractor will be here putting in forms. Soon cement trucks will be rumbling up and down the hill from Mohave Valley. And, over the next five or six months, our beautiful new library building, constructed in the image of the old (1900-1956) Goffs railway depot, will take shape.