Report and photo by Dennis Casebier
It turned out to be a beautiful day and the workers took full advantage of it. It was 25 degrees on our front porch at 6:15 AM. The Cordova crew showed up a little before 7:00 AM.
The builders got the corrugated siding installed on the west side of the Freight House, but not yet on the south end. The yellow lap siding all around the two-story Depot section looks to be mostly completed. Also they got the green paint on the fascia board all around the building today. They were staying later than usual today because of the improvement in the weather.
Dan said he needs to finish the siding and the roofing and after that it will be mostly various subcontractors installing insulation, electrical, drywall, etc. The electrical is a biggie. He said he had hopes the electrician will be here in about two weeks.