Report and photos by Dennis Casebier
The rain gutter guys (three of them) showed up this morning. Jo Ann and I were just leaving for a quick business trip into town. I figured they would still be here when we got back at about 2:00 PM, but they were gone already. Hugh reports the job took about four hours. So the gutters are all in place.
Also, Dan Cordova and a helper were here this morning finishing up the bollards they started yesterday. These are metal posts designed to prevent people from driving their vehicles into the new building.
The plumber is expected to be back on Saturday of this week to fix a leak that has developed in one of the walls.
Dan is picking off the few remaining tasks. The last big one will be to put the flooring down and I understand that is to be done next week.
We are nearing completion.