Report and photos by Dennis Casebier

The flooring crew, consisting of Kelly Binns, Ed Hardesty, and Donna May, arrived mid-morning. They started on the first floor of the Depot.

First they cleaned the floor, then put down some kind of foam sheeting, and now they are laying maple tongue and groove pattern, perco-type flooring on top of that. At 2:00 PM they were about two-thirds of the way done with that room.

Here at the end of the day, the flooring is complete on the first floor of the Depot. Also they've cleaned the floor in the lounge and bathroom and are putting glue down. We are asked not to go in there this evening or we might have to stay forever!

The crew is moving all of their tools and materials to the second floor. This same flooring goes in the second floor of the Depot. Then they'll lay a vinyl material of the same maple style in the Lounge and rest room.

A window guy is here working on loose molding. There'll be some other glass guy later to replace some of the glass upstairs.

Very warm and windy today but it isn't impacting their work day since the workers are inside.