Report and photo by Dennis Casebier
General Contractor Cordova with two men spent the day here. They were taking care of some odds and ends. The most significant task was to finish off the staircase on the steps to the second floor of the Depot. They did that and it looks very nice.
Also today Phil Motz and Gus and Stella Lind strung wire to some ceiling fan positions in the new building that had not been on the original plans and hence had not been put in place.
Perhaps most importantly, we finalized the plans today for that portion of the water system that will provide water for fire fighting around the new building. Now it will be only a matter of several days and we'll have that system in.