Dennis Casebier, John Harrington, and Ron Shepard pulled the Big Tex trailer to Bullhead City to procure lumber and other materials for the new Pump House. Construction was commenced today by Ron Shepard and John Reiff.
Saturday, March 17, 2007
Thursday, March 15, 2007
Power House roofed
From the Mojave Road Report
Ron Shepard and John Reiff put roofing on the new Power House.
Ron Shepard and John Reiff put roofing on the new Power House.
Wednesday, March 14, 2007
Pump House pour
From the Mojave Road Report
John Harrington, John Reiff, Ron Shepard, and Carl Weikel poured the concrete slab for the new Pump House and also a step at the new Power House.
John Harrington, John Reiff, Ron Shepard, and Carl Weikel poured the concrete slab for the new Pump House and also a step at the new Power House.
Trench dug from street to Power House
Saturday, March 10, 2007
We con duit
From the Mojave Road Report
Bobby and Tom Smith and Don Johnson were here working on a ditch for the conduit that will carry the new electrical service to the new Power House. Tom also did maintenance on the Greening tractor.
Bobby and Tom Smith and Don Johnson were here working on a ditch for the conduit that will carry the new electrical service to the new Power House. Tom also did maintenance on the Greening tractor.
Friday, March 2, 2007
Pump House preparation
From the Mojave Road Report
John Harrington commenced work on the foundation forms for the Pump House that will support the new well. John Reiff finished restoration fo the Slaughter cement mixer. Its first job will be to pour the Pump House foundation.
John Harrington commenced work on the foundation forms for the Pump House that will support the new well. John Reiff finished restoration fo the Slaughter cement mixer. Its first job will be to pour the Pump House foundation.