Wednesday, May 14, 2008

Roof braces installed

Report and photos by Dennis Casebier

The painters are here. They got the first of two finish coats applied on the interior of the Library/Depot.

Mr. Cordova was here with a small crew this morning and into the afternoon. He won't be back personally now until early next week, but his crew will continue working on the roof braces.

Warm here today - we hit 100 degrees on the front porch. No wind this morning but it came up this afternoon.

Monday, May 12, 2008

Interior painting prep work

Report and photos by Dennis Casebier

The paint crew has been at work preparing the interior of the Library/Depot for painting. They haven't started painting yet. They're just getting ready.

Wednesday, May 7, 2008

Trimming the windows

Report by Dennis Casebier

General Contractor Dan Cordova and crew arrived early this morning and have been out there working in the building all day.

They have trim around the windows, the wainscot, or chair rail, in place in the fist floor of the depot, and much of the crown molding is installed.

Mr. Cordova reports they plan to be here through Friday and have the interior ready for painting, which should commence the beginning of next week.

Monday, May 5, 2008

Door hardware and trim installed

Report and photos by Dennis Casebier

After a break of a couple of weeks, general contractor Dan Cordova and his crew of four are back early this morning on the job. They labored much of the day putting trim on doors, installing some new doors, and installing door knobs, etc. They left this afternoon returning to Yucca Valley.

Also, they are installing moulding around windows and doors and crown moulding around the top of the walls in some rooms. This will prepare the building for interior painting. They'll be back tomorrow. Their goal is to have the interior ready for painting which could begin a week from today.

Beautiful day today. The temperature was about 80 degrees with very little wind.

Friday, May 2, 2008

Water pressure system installed

Report and photo by Dennis Casebier

Tim and Alfonzo of Eagle Well Drilling and Pump Service showed up at 7:30 AM this morning and were here all day. They finished up at almost dark this evening. The pressure tank and booster pump system is completely installed.

A decision was made to reduce the number of pressure tanks from four to three. This was mainly due to the amount of space in the Pump House. Then, there was a mishap towards the end of the installation.

The system was fully pressurized when a union gave way inside the Pump House and Wooooosh! All of the water from the pressure tanks was released into the Pump House. Quite a mess. It took them a couple of hours to recover from that.

Looking forward, it is anticipated that general contractor Dan Cordova and his subconractors will recommence work on the Library/Depot this coming week.

Wednesday, April 23, 2008

Phone lines installed

Report by Dennis Casebier

Two AT&T trucks with cherry pickers arrived at a little after 9:00 AM to run our phone lines to the west side of Lanfair Road. Phil is out there with them. It's not cold out but there is a very strong wind blowing, mostly out of the west.

Monday, April 21, 2008

Interior walls are textured

Report by Dennis Casebier
Photos by Dennis Casebier and Chris Ervin


The "mudders" were here fairly early this morning. They've had their special mixer machine chugging away over there all day. Right now it is quiet. That's because they've finished! The mudding and texturing is done and they are now cleaning up. They won't be back tomorrow.

Also today Phil Motz and Gus Lind worked on the water system with the result that the new well and associated pressure tank are now on line. There is water pressure down to the edge of the Library/Depot. All Mr. Cordova will have to do to put water in the building is turn one valve at the edge of the building.

With the drywall and mudding done that means the interior of the building will be ready for painting. After the painting the electrical fixtures can be put on. After that flooring can be put down. We're rolling along!

The wind we had over the weekend has continued, although today it is somewhat diminished. The temperatures have continued warm.

Thursday, April 17, 2008

Mudders and railfans

Report by Dennis Casebier
Photos by Chris Ervin


The "mudders" were here all day "mudding." Much progress is being made. Building inspector Steve Given showed up this afternoon and completed the "drywall nailing" inspection. This is something of a misnomer since they use screws not nails. Steve signed in the appropriate space on our inspection card and the job progresses right along.

Also today, a man named Glen Icanberry showed up with a friend of his named Vic Neves. They are both rail buffs. Glen was here a month or so ago and at that time he said he had the big part of the semaphore signal we need to go in front of the depot. At that time he said he'd been looking for a home for it and I said, "look no further!"

Well, today he and Ivan showed up with not only the semaphore mechanism but also official Santa Fe plans for installing and maintaining it. Glen also brought other documentary materials relating to the Goffs Depot and other depots like it. Vic is a railroad photographer and has written several books about railroading, mostly Southern Pacific.

Charlie and Kathy Connell of Phoenix arrived for the Encampment today. They spent much of the day picking nails up (with a magnet) around the Library/Depot and then they carefully raked the area. Also they did some repair to the tortoise fence.

Monday, April 14, 2008

Rough drywall finished

Report and photo by Dennis Casebier

At about 7:00 AM this morning I saw someone out by the Library/Depot so I went over to check it out. It turned out to be a return of the drywallers who were here yesterday. I thought they finished the first phase of dry-walling yesterday but they hadn't. They plan to finish today. They informed me that Randy, their boss, is to be here today. He'll set the next phase of dry-walling in motion -- the "finish" work, or mudding.

Saturday, April 12, 2008

Ready to fight a fire!

Report and photos by Dennis Casebier

The drywallers were here through some time today. Phil informs me they didn't quite finish and they plan to come back tomorrow.

The hydrant for the Library fire protection system was completed before noon today and water flowed! Phil Motz came over the FRS announcing that the two 5,000 gallon tanks were approaching "full." He called a gathering at the hydrant at 6:15 PM for anyone interested.

There was a ceremonial opening of the valve with the tanks pretty much full to see how far the hydrant would fling water -- proving once again we'll grasp most any opportunity to have a celebration out here! It threw water seven feet from the hydrant under the force of gravity alone.

Gus and Stella Lind, Kristy and Phil Motz, and Mark Wire wrestled the water project to completion this morning. Congratulations and thanks to all who helped with this over the past several weeks.

Thursday, April 10, 2008

Drywallers begin and 6-inch line fetched

Report and photos by Dennis Casebier

The drywallers showed up fairly early this morning and are well into the job. The fellow in charge on site told me they expect to be completed by Sunday. The guys here now just do the initial installation and others come along behind them to do the finish work.

Gus Lind and I went into Fort Mohave and Bullhead City to procure the supplies for the fire protection water system as well as conduit for telephone lines.

The ditch for the 6" line is about complete. Gus hopes to complete it this afternoon. Then I expect installation of the new line and hookup of the two 5,000 gallon water tanks to the 6" line and a hydrant will get installed over the next two days.

Wednesday, April 9, 2008

Water line dug

Report and photos by Dennis Casebier

Lots going on at Goffs today. We closed the day yesterday with a terrific wind. By this morning it had died out. But not for long. It started up again mid-morning and here at mid-afternoon it is a strong wind again.

General Contractor Dan Cordova and two of his guys were here this morning early. They had intended to put thresholds down at the doors. They did some of the prep work but that's about it.

The bad news is that Dan discovered pretty serious damage to a couple of the doors. They were left open, a strong wind caught them, and the result is split wood on the frames. Dan is assessing the damage and what it will take to fix it.

Building Inspector Steve Given was here this morning. He inspected the insulation job and the septic system. We passed in both categories.

As I write this Gus and Phil are out there digging the ditch for the water line that will connect the two 5,000 gallon water tanks with a hydrant required by the County Fire Department. Gus Lind and I will be going into Fort Mojave tomorrow morning to pick up the six inch water pipe. It will take another day to bury the pipe and make the necessary connections to be fully up to speed on this.

Gus Lind was at the controls of the Greening Tractor digging the water line ditch. Gail Andress is off for a couple of days on sick leave, but you can't hold him down long.

The drywall for the interior of the entire Library/Depot building was delivered this morning. It was off-loaded by hand into the rooms where it'll be needed. I believe the dry-wallers may be here to begin their work as early as tomorrow.

Tuesday, April 8, 2008

Insulation inside

Report by Dennis Casebier
Photo by Hugh Brown

The insulators showed up this morning a little before 9:00 AM. There were three people from Desert Insulation. The fellow in charge was Gary Fraser and the other two were brothers Ramino Rizo and Genaro Rizo.

To our amazement they had all the insulation installed in the space of about five hours. They were done and heading out the gate by about 1:00 PM or so. Amazing.

It is much quieter in the building now and we are understanding the drywallers will be here on Friday.

Temperatures were moderate all day but quite windy.

Saturday, April 5, 2008

MDHCA board reviews progress

Report by Chris Ervin

Today, during a break from the regularly scheduled meeting, the MDHCA Board of Directors did a walk-through review of progress on the Library/Depot construction. Executive Director Dennis Casebier and Director Chris Ervin met with general contractor Dan Cordova to discuss upcoming work scheduled over the next couple of weeks.

Friday, April 4, 2008

Security system wired, part 2

Report by Dennis Casebier

Michael and Rene Howser of EES, a security firm, were here stringing wires for about an hour for the security system in the Library/Depot. With the completion of their work the walls in the interior of the building can now be closed. Hence, general contractor Dan Cordova has scheduled installation of insulation for next week and installation of drywall for the week after.

Wednesday, April 2, 2008

Stairway to second floor finished

Report and photo by Dennis Casebier

General Contractor Cordova with two men spent the day here. They were taking care of some odds and ends. The most significant task was to finish off the staircase on the steps to the second floor of the Depot. They did that and it looks very nice.

Also today Phil Motz and Gus and Stella Lind strung wire to some ceiling fan positions in the new building that had not been on the original plans and hence had not been put in place.

Perhaps most importantly, we finalized the plans today for that portion of the water system that will provide water for fire fighting around the new building. Now it will be only a matter of several days and we'll have that system in.

Saturday, March 29, 2008

Security system wired

Report by Dennis Casebier

Dave Mongrain of Alarm Team arrived yesterday and began installing the wire necessary for the security system for the interior of the Library/Depot. He spent the night and finished up that part of the installation by early this afternoon. He'll be back when the drywall is in place to install the security system hardware.

Thursday, March 27, 2008

Ready to go

Report by Dennis Casebier
Photos by Dennis Casebier and Roger Mitchell


Today, the "A" Team, consisting of Phil Motz (in charge), Gail Andress, Gus & Stella Lind, and Morris Swain assembled on the west side of the Library/Depot with all the materials in hand to install the septic system that will support the new facility.

At the controls of the Jack & June Greening Tractor, Gail Andress did the digging, with shovel accompaniment provided by the Linds and Morris Swain.

With the big hole dug, Gail lowered the new 1,000 gallon septic tank into the hole.

Meanwhile, the crew had the sewer line ready to connect from the building.

Gail then dug the ditch for the 50-foot leach line and dumped the required amount of leach rock in the bottom. The leach line was laid on the rock and more rock placed on top of that -- according to code.

The job will be finished tomorrow by laying newspaper on top of the rock on top of the leach line. Then the whole thing will be covered with dirt.

While the leach line was being laid the new septic tank was filled with water. Next thing you know, we'll be almost "ready to go," so to speak.

Wednesday, March 12, 2008

Tanks, a lot

Report and photos by Dennis Casebier

We are experiencing beautiful weather. Our high temperature today was over 80 degrees with only a breeze. Things have been pretty quiet around the construction site for the past several days, until today.

Rudy of C & R Tanks of Tulare, CA arrived at about 10:00 AM with our truck load of tanks. We led him in through the service entrance and up to the job site. He nosed his big rig out towards the Stotts Stamp Mill gate and then backed in along side the pad constructed by Gail Andress where the two 5,000 gallon tanks are to go.


The straps were removed from the three round tanks, they were rolled off, shifted into position, and set down. The whole process took no more than 30 minutes. We positioned the big tanks so their fill holes and drains line up with about six feet between them. This will facilitate getting them all hooked up to the water system.


For the fourth tank, the 1,000 gallon septic tank, a different procedure was used. Gus and Morris put straps around the tank then lifted it off the truck with the Greening Tractor. The tank was then moved over near the spot where it is to be buried.


The total delivery was of two 5,000 gallon water tanks for fire fighting purposes, one 2,500 gallon tank for potable water, and one 1,000 gallon sepic tank.

Thursday, March 6, 2008

The roof is complete

Report and photo by Dennis Casebier

The wind came back before dawn this morning. The temperature on front porch at 6:15 AM was a hair below 40 degrees. It must have gotten a little colder during the night because we had a thin sheet of ice on the bird water.

The roofers came back a little before 10:00 AM and they a re out there in the cold wind now on the tall ladders trying to get roofing on the top of the depot. That roof is steeper than the roof on the Freight House.

And now, here in the early afternoon, the roofing is on the second story of the Depot. The wind is still blowing and it's cool out even though it's bright and sunny. The roofers are still working on the details, but basically, the roof is on and completed.

Wednesday, March 5, 2008

Combo inspection

Report by Dennis Casebier

The temperature on the front porch was about 40 degrees at 6:15 AM. That's the good news. The bad news is that it was blowing a gale out there again. We had a one-day respite, yesterday.

The inspectors - Steve Given and Gary Given - showed up earlier than expected. John Harrington and I went out and stayed with them in the cold wind for the better part of two hours. Fortunately Dan Cordova, who fully intended to be here while the inspectors were here, showed up after the first hour or so. They did a pretty thorough inspection and found a few things that needed attention. In the end they signed off on the "combo" inspection. The next step will be insulation and then onward to drywall.

This was Gary Given's last inspection visit to our site due to his impending retirement. We reflected over the development that has taken place here over the past 18 years and he expressed himself proud of what has been accomplished.

In the midst of the inspection, the roofers arrived (to my amazement considering the wind storm), and began to work.

I didn't get to go off on my "morning" walk until about 5:00 PM this afternoon. By the time I got northward up to where I normally stop, the wind had quit. I did an about face and headed back down the hill. As I approached the fence line I thought sure I heard the sound of a nail gun. So I cut through the creosote bushes down to the construction site. By the time I got there it was nearly dark.

Sure enough, the roofers were up there putting the finishing touches on the east roof of the Freight House. I stopped and visited with them a bit and then came on home. It is heartening to see Americans working hard. And they are doing a good job, too. There are so many these days that want everything for nothing. They said they'll be back tomorrow to finish the roof over the depot. They wanted to know if I liked the way it looked. Of course we do. They, like every other one of the subcontractors hired by Dan Cordova have done excellent work.

Tuesday, March 4, 2008

Roofers on a catwalk

Report and photo by Dennis Casebier

It has been a nice, but busy day. The low was just below freezing overnight, enough to put a little ice on the bird water. But generally speaking the weather was nice all day.

The roofers showed up at about 10:00 AM. They come late and work late. For example, here it is 5:30 PM and I can look out my window across the street and they are still there. They are working on the high roof over the two story Depot. They don't have a lift so they are using ladders. It gives me the willies just to watch them. But they are getting the roof covered.

Tomorrow we are scheduled for what is called a "combo" inspection by the Department of Building and Safety of San Bernardino County. This includes an inspection of the electrical and a bunch of other stuff all at the same time. So, in the life of a construction project, this is exciting stuff.

Also the telecom guy is going to be here in the neighborhood on other business tomorrow, so we'll be chatting with him about phone lines for the new building.

John Harrington arrived back from his extended trip to Michigan and Florida. He'll be here until about the 17th of March when he plans to leave indefinitely. Hopefully he'll come back someday. It has been a joy to have him here. And he did a lot of good work. Highlights in his accomplishments are painting almost all the buildings and the construction of the Library/Depot model that so many have enjoyed seeing in the Schoolhouse and the top of this page.

Monday, March 3, 2008

West side Freight House roofing finished

Report and photo by Dennis Casebier

The wind blew all night and was blowing some when we got up this morning, but it wasn't real cold at 39 degrees on the front porch. I figured not much work would get done, but then along about mid-morning, things began to happen.

First the roofers showed up. Three guys altogether. Then the wind slacked off. They've been working steadily out there ever since. It appears they'll get the roof on the west side of the Freight House done today. They are hopeful of finishing the whole roofing job by Wednesday. They have not started on the roof over the two-story part. But Mr. Cordova told me they plan to have a different crew out here tomorrow to do that portion and likely they'll finish it tomorrow.

I went over to the job site again at 3:00 PM and saw the roofers had finished the roofing on the west side of the Freight House. They were up on the tall ladders working on the west edge of the roof over the two-story part. I expect they are serious about getting that done tomorrow. The roof on the east side of the Freight House isn't completed yet, but it will be easy compared to the roof over the two-story part.

Friday, February 29, 2008

Warm leap day

Second floor bay windows letting in the morning light. Photo by Chris Ervin


Report by Dennis Casebier

Beautiful day today. The temperature hit 85 degrees on our front porch. There was very litle breeze.

The roofers showed up at 11:00 AM and tend to work late. Likely it is that they don't want to start laying shingles until it warms up and then they like to keep going. A little less than half the roofing is laid on the east side of the Freight House and they have begun to work on the west side. No work yet on the roof over the second story of the Depot.

The electricians did not come back today. We are well into the time for each of the "trades" to do their job.

Wednesday, February 27, 2008

Roofers arrive!

The roofers arrived to this scene on the west side of the Freight Building roof.


Report by Dennis Casebier

It was a beautiful day all day today. The temperature was well over 80 degrees in the afternoon. I'm seeing ants beginning to clean out their nests, lizards scurrying around, and sparrows hurrying everywhere with nesting material.

The two electricians were here all day. They are nearly finished.

A man was here this afternoon to develop a bid to put in some security features on the new building.

Then late this afternoon, the roofing crew showed up under the direction of Fred Carrido of Alpine Roof Company. Gus and I went out to connect with him. Fred was determined to get started this afternoon.

He has brought some special material with him to put down on the roof to serve as an undercoat. It was late in the afternoon but they not only unloaded, but got up on the roof and started to work.

In fact, here at 5:30 PM they are still up on the roof working. They won't be able to work much more, but the days are getting longer. They are to come back tomorrow and Friday and plan to finish up next week.