Sunday, April 22, 2007

Spring Encampment volunteer efforts

Report by Phil Motz

In anticipation of the Encampment, John Harrington had acquired the 4-inch, 2-inch, and 1-inch conduit for the electrical lines for the Power House and Pump House buildings. Robert Botich dropped off fluorescent fixtures for both buildings and a 100-amp panel for the Pump House.

The fire break west of the library site was established by a crew consisting of John Harrington, Red Brooke, Sharon Holmes, Larry Burkholder, Chris and Leslie Ervin, Kib and Shirley Roby, and Jackie Ridge.

Kib Roby manicured the new well site.

The conduit for the 400-amp incoming electrical service was put in place.

Saturday, April 7, 2007

New electrical service planned

Report by Dennis Casebier

Robert Botich, an electrician by trade, traveled from Corona to Goffs and met with Dennis Casebier, Phil Motz, and John Harrington to review Southern California Edison (SCE) electrical specifications and to plan out acquisition of 400-amp meter and circuit panel.