Saturday, March 17, 2007

Pump House materials run

From the Mojave Road Report

Dennis Casebier, John Harrington, and Ron Shepard pulled the Big Tex trailer to Bullhead City to procure lumber and other materials for the new Pump House. Construction was commenced today by Ron Shepard and John Reiff.

Thursday, March 15, 2007

Power House roofed

From the Mojave Road Report

Ron Shepard and John Reiff put roofing on the new Power House.

Wednesday, March 14, 2007

Pump House pour

From the Mojave Road Report

John Harrington, John Reiff, Ron Shepard, and Carl Weikel poured the concrete slab for the new Pump House and also a step at the new Power House.

Trench dug from street to Power House

Report by Dennis Casebier

An underground conduit trench was dug with volunteer labor between the Lanfair Road and the new Power House. The incoming new electrical service will be laid under the Blvd. of Dreams.

Saturday, March 10, 2007

We con duit

From the Mojave Road Report

Bobby and Tom Smith and Don Johnson were here working on a ditch for the conduit that will carry the new electrical service to the new Power House. Tom also did maintenance on the Greening tractor.

Friday, March 2, 2007

Pump House preparation

From the Mojave Road Report

John Harrington commenced work on the foundation forms for the Pump House that will support the new well. John Reiff finished restoration fo the Slaughter cement mixer. Its first job will be to pour the Pump House foundation.